Warehouse, industrial unit & logistics fit-out · Dubai

What a warehouse conversion actually costs.


A warehouse has two cost bases inside one building, and blending them into a single rate per square foot is how industrial budgets go wrong. This page prices both separately, from our own rate card.

AED 90–180per sq ft, office block
AED 17per sq ft, warehouse floor
6–12weeks on site, 10,000 sq ft
2026rates on this page
The thesis

One building, two cost bases.

This is the thing almost every industrial estimate gets wrong. An office and amenity block inside a warehouse prices like an office — partitions, ceilings, joinery, air-conditioning, data, sanitaryware. The warehouse floor prices like civil work — slab preparation, a resin floor, high-bay lighting, fire services, and very little else. The two differ by a factor of five or more per square foot, so a single blended rate is only correct for the exact office-to-warehouse ratio it was derived from.

What drives the office block
  • Area, and whether it is single storey or a mezzanine
  • Partition and glazing density; meeting and manager rooms cost more than open floor
  • Air-conditioning — usually fan coil units and ducted zones, a load the shell may not have
  • Sanitary and ablution provision against headcount
  • Data, comms room and the power the office imposes on the shell's distribution
  • Joinery — reception, pantry, workstation runs
What drives the warehouse floor
  • Slab condition, flatness and moisture content — tested, not assumed
  • Resin system and build thickness against the actual traffic: pallet trucks, reach trucks, or loaded forklifts
  • High-bay lighting layout and emergency lighting coverage
  • Fire detection, hose reels and sprinkler interface, which racking height changes
  • Line marking, anti-slip to ramps, and loading-bay details
  • Whether the existing floor comes up, and where the waste legally goes
Office and amenity standardWhat it isTurnkey, per sq ft
Basic staff and amenity blockPainted partitions, mineral tile ceiling, carpet tile, WCs and ablution, pantry, split or fan coil units, basic data — the standard priced in the worked example belowFrom about AED 90
Standard office blockBetter ceiling and lighting, some glazed partitions, meeting room, proper reception joinery, ducted air-conditioning, structured cablingAbout AED 130
Fitted office or showroom standardGlazed offices, feature reception and ceiling, raised access floor, higher specification joinery and finishes, full zoned air-conditioningFrom AED 180

This is the ladder people mean when they argue about the rate. All three are the same floor area; the difference is specification, and it is roughly two to one from bottom to top. Decide where on it you want to sit before you compare quotations, because two contractors quoting different rungs are not quoting the same job. These rates sit below the equivalent in a commercial tower — see our office fit-out cost page — because an industrial unit carries no landlord handbook, no service-lift booking and far simpler access.

Our rate card

The numbers other guides do not publish.

These are our 2026 starting rates, the same ones we quote from. They assume a sound shell, normal access and daytime working. Build your own estimate, then let us survey and fix the price in writing.

ElementUnitFrom
Industrial unit conversion — fitted office or showroom standardper sq ftAED 180
Industrial unit conversion — basic staff and amenity blockper sq ftAED 90
Epoxy and PU resin floorsper sq mAED 90
Polished concrete floorsper sq mAED 85
Substrate grinding, levelling and moisture testper sq mAED 40
Anti-slip treatmentper sq mAED 45
Demolition and strip-outper sq mAED 55
Strip-out and make-goodper sq mAED 45
Waste handling and certified disposalper loadAED 850
Site and yard worksper packageAED 25,000
Gate, barrier and perimeter worksper installationAED 18,000
Façade and high-level accessper dayAED 6,500
Gypsum partitionsper sq mAED 110
Mineral tile ceilingper sq mAED 75
Gypsum false ceilingper sq mAED 85
Glazed and frameless partitionsper sq mAED 480
Carpet tile and raised access floorper sq mAED 75
Floor and wall tiling, supply and fixper sq mAED 95
Paintingper sq mAED 14
Joinery — reception, pantry, workstationsper linear metreAED 1,900
Doors and ironmongery, supplied and hungper leafAED 1,450
Fan coil or split air-conditioning, installedper unitAED 2,400
Ductwork, grilles and air balancingper zoneAED 4,500
Distribution board, sub-mains and final circuitsper boardAED 3,500
High-bay, general and emergency lightingper pointAED 85
Data cablingper pointAED 250
Plumbing and sanitarywareper fixtureAED 450
Grease trap and drainageper installationAED 6,500
Fire hose reel and interface worksper pointAED 2,800
Signage and wayfindingper signAED 350
Measured survey and space planper unitAED 1,500
Authority submittals and NOCsper submissionAED 2,500
Post-construction cleanper sq mAED 12
As-built drawings and O&M handover fileper projectAED 2,000

All figures exclude VAT and are starting rates for 2026. Structural steel, mezzanine framing, racking, dock levellers, cold-store panels, compressed air and process services are quoted on drawings and are not per-square-metre items.

Worked example

A 10,000 sq ft unit, priced in three blocks.

An existing warehouse shell of roughly 929 square metres: a 2,000 square foot single-storey office and amenity block at the basic standard from the ladder above, 8,000 square feet of warehouse floor on a resin system, and the site and enabling works around both. Daytime working. Move the office to the fitted standard and the project total rises by roughly AED 180,000 without a square foot changing.

LineQuantityRateAmount
Gypsum partitions150 sq mAED 110AED 16,500
Glazed and frameless partitions24 sq mAED 480AED 11,520
Mineral tile ceiling186 sq mAED 75AED 13,950
Doors and ironmongery8 leavesAED 1,450AED 11,600
Painting480 sq mAED 14AED 6,720
Carpet tile and raised access floor186 sq mAED 75AED 13,950
Tiling to WCs, ablution and pantry45 sq mAED 95AED 4,275
Joinery — reception, pantry, workstation runs14 lin mAED 1,900AED 26,600
Fan coil air-conditioning6 unitsAED 2,400AED 14,400
Ductwork, grilles and air balancing2 zonesAED 4,500AED 9,000
Distribution board and final circuits1 boardAED 3,500AED 3,500
Lighting and emergency lighting, tested56 pointsAED 85AED 4,760
Data cabling and comms room24 pointsAED 250AED 6,000
Plumbing — WCs, ablution, pantry12 fixturesAED 450AED 5,400
Subtotal — office and amenity block, 2,000 sq ftAED 148,175
Strip-out and make-good200 sq mAED 45AED 9,000
Waste handling and certified disposal8 loadsAED 850AED 6,800
Substrate grinding, levelling and moisture test743 sq mAED 40AED 29,720
Epoxy or PU resin floor743 sq mAED 90AED 66,870
Anti-slip treatment to ramps and wet areas60 sq mAED 45AED 2,700
High-bay and emergency lighting, tested64 pointsAED 85AED 5,440
Distribution board and sub-mains1 boardAED 3,500AED 3,500
Fire hose reel and detection interface4 pointsAED 2,800AED 11,200
Signage, line marking and wayfinding10 signsAED 350AED 3,500
Subtotal — warehouse floor and envelope, 8,000 sq ftAED 138,730
Measured survey and space plan1AED 1,500AED 1,500
Authority submittals and NOCs2AED 2,500AED 5,000
Gate, barrier and perimeter works1AED 18,000AED 18,000
Site and yard works1 packageAED 25,000AED 25,000
Post-construction clean929 sq mAED 12AED 11,148
As-built drawings and O&M handover file1AED 2,000AED 2,000
Subtotal — site, enabling and handoverAED 62,648
Elemental sum, 10,000 sq ft unitAED 349,553

Note what the three subtotals say. The office block is AED 74 per square foot of measured work at the basic standard. The warehouse floor is AED 17 per square foot. The blended figure across the whole unit is AED 35 per square foot — and it would move by half if you changed the office from 2,000 square feet to 4,000, or doubled if you took the office to the fitted standard. That is the argument against blended rates, in one table.

From measured work to a real priceAmountPer sq ft
Elemental sum — the table aboveAED 349,553AED 35
Preliminaries, site establishment, plant and access, supervision, insurances, contractor’s overhead and profit — 15% to 22% on a unit this sizeAED 52,447 to AED 76,447AED 5 to AED 8
Turnkey conversion, fixed in writingAED 402,000 to AED 426,000AED 40 to AED 43
Structural steel, mezzanine, racking, dock levellers, cold store, process servicesQuoted on drawings—

We would rather show you the step from measured work to price than fold it into a rate and let you discover it at tender. If another contractor’s per-square-foot figure is lower than this, ask which of the lines above sits inside it.

Approvals

Mainland, free zone and Trakhees are not the same route.

Industrial fit-out approvals in Dubai depend on where the unit sits, and getting the route wrong is the most expensive mistake available at the start of a job. Confirm the current requirements with the relevant authority — we re-check them at every survey rather than working from a saved checklist.

Where the unit isWho permits the worksWhat else applies
Mainland DubaiDubai Municipality fit-out or building permitCivil Defence approval before construction; DEWA application on load change
JAFZA, DAFZA, Dubai South, Dubai Industrial City, Dubai Investments ParkThe zone authority, in place of the municipalityZone contractor registration, works permit, deposits, zone fire requirements
Jebel Ali and Dubai World Central areas under TrakheesTrakhees — Ports, Customs and Free Zone CorporationTrakhees EHS requirements and its own inspection regime
Northern emirates — RAKEZ, SAIF, Ajman and Sharjah industrialThe emirate or zone authoritySeparate contractor registration per zone

Regardless of route: Civil Defence governs fire detection, hose reels, sprinkler interface and escape; demolition waste must go to an approved facility with certified disposal; and a mezzanine, a change of activity, or racking above the permitted height brings structural and fire review that a fit-out permit alone does not cover.

What catches people out
  • Contractor registration in a free zone takes time and cannot be done retrospectively
  • A mezzanine changes escape travel distance and the sprinkler design, not just the floor area
  • Electrical load for an office block plus process equipment often exceeds the shell's existing supply
  • Racking height can trigger in-rack sprinklers, which is a different order of cost
  • Certified waste disposal is a documented requirement, not a skip hire decision
What we run in parallel
  • Measured survey and space plan while pricing, not after award
  • Structural check on the slab and any proposed mezzanine
  • Fire strategy review against the proposed layout before drawings are issued
  • DEWA load assessment against the combined office and process demand
  • Long-lead items — resin materials, steel, air-conditioning plant — identified at survey
The floor

Why a quarter of the budget sits on the slab.

In the worked example above, substrate preparation and resin together come to AED 96,590 — about a quarter of the whole project. That is not a padded line. It is the difference between a floor that lasts and a floor that has to be relaid, which means emptying the building a second time.

What we do before any resin is mixed
  • Diamond grinding or shot blasting to a sound, open profile
  • Moisture content tested and recorded — the single most common cause of resin failure
  • Levelling screed where the slab falls outside tolerance
  • Crack and joint detailing, which a coating will otherwise telegraph within months
  • System and thickness selected against the actual wheel loads, not a generic specification
What we match the system to
  • Pallet trucks and foot traffic — a coating is usually enough
  • Reach trucks and loaded forklifts — a screed or self-levelling build
  • Wash-down, chemical or food areas — PU rather than epoxy, with coved detailing
  • Loading bays and ramps — anti-slip aggregate as a specified line, not an afterthought
  • Cold or temperature-controlled areas — system and cure regime chosen for the condition

Epoxy and resin flooring in Dubai

Specialist and commercial flooring

Interior and commercial fit-out

Office fit-out cost in Dubai

Clinic and medical centre fit-out cost

MEP and technical services

Programme

What six to twelve weeks actually looks like.

StageTypical durationRuns in parallel with
Measured survey, slab assessment and space plan1 weekAuthority route confirmation
Permit and Civil Defence submissions4–8 weeksContractor registration where the zone requires it
Strip-out, make-good and certified disposal1 weekMaterial procurement
Office block first fix — partitions, MEP containment1–2 weeksSlab grinding and moisture testing
Resin floor — preparation, application, cure1–2 weeksNo other trade on the slab
Office ceilings, second fix MEP, finishes2 weeksJoinery manufacture off site
High-bay lighting, fire services, line marking1 weekAir balancing
Site and yard works, gate and perimeter1–2 weeksSignage production
Testing, inspection and sign-off1 weekSnagging
Clean and handover2–3 daysAs-built and O&M file

The resin floor is the critical path and it does not compress. Everything else can be resequenced around it; the cure cannot.

Questions

Common questions.

How much does a warehouse fit-out cost in Dubai?

There is no single rate, and anyone quoting one for a whole unit is guessing. A warehouse has two completely different cost bases inside one building. The office and amenity block prices like an office: from about AED 90 per square foot for a basic staff block to AED 180 per square foot and up for a fitted office or showroom standard. The warehouse floor prices at around AED 17 per square foot, because it is substrate preparation, a resin floor, high-bay lighting and fire services and almost nothing else. Blend the two across the 10,000 square foot unit in our worked example and you get about AED 35 per square foot — true for that unit, misleading for any other, because it depends entirely on how much of the floor plate is office and to what standard.

Why do you price the office and the warehouse separately?

Because the ratio between them is the single biggest variable in an industrial job, and a blended rate hides it. A 10,000 square foot unit with a 1,000 square foot site office is a different project from the same shell with a 4,000 square foot showroom and mezzanine offices, and the difference is several hundred thousand dirhams. Price the two areas on their own bases and the estimate survives a change of layout. Price it per square foot of total area and it does not.

What approvals does an industrial fit-out need?

On mainland Dubai: a fit-out or building permit from Dubai Municipality on architectural and MEP drawings, Civil Defence approval of the fire and life-safety drawings before construction starts, a DEWA application where the electrical load or metering changes, and certified disposal of demolition waste to an approved facility. In a free zone — JAFZA, DAFZA, Dubai South, Dubai Industrial City, Dubai Investments Park, or RAKEZ and SAIF in the northern emirates — the zone authority replaces the municipality and runs its own contractor registration and works permit. Trakhees governs several Jebel Ali and Dubai World Central areas. Mezzanines, racking over a certain height, and any change of activity bring additional review. We confirm which route applies at survey, because the wrong one costs weeks.

Can you put a mezzanine or office pod in an existing warehouse?

Usually, and it is one of the most common scopes we price — but it is a structural and fire question before it is a fit-out question. A mezzanine changes floor loading, escape travel distances and the sprinkler and detection design, and it needs structural drawings and Civil Defence sign-off, not just a partition layout. We survey the slab and the existing fire strategy first and tell you what the unit will actually carry.

How long does an industrial unit conversion take?

Six to twelve weeks on site for a straightforward 10,000 square foot conversion, with the resin floor as the critical path — substrate preparation, moisture testing, application and cure cannot be compressed, and nothing else can be happening on that slab while it runs. Approvals add four to eight weeks in parallel. A free-zone contractor registration, if we do not already hold one for that zone, is worth checking at the start rather than at week three.

Why does the floor cost so much of the budget?

Because in a warehouse the floor is the structure you use. In the worked example below, preparation and resin together are about a quarter of the whole project — and that is the right place for the money. A resin floor laid over an untested slab lifts, and relaying it means emptying the building again. We grind, level and moisture-test as a priced line item, every time, and we would rather lose a job on that line than come back to it.

Do you work in units that are still operating?

Yes. Phased resin flooring in a working warehouse is a sequencing problem — bay by bay, with racking decanted, containment up, and each bay returned to use as it cures. Roughly half of what we have delivered has been executed in premises that stayed open, including occupied government hospital departments, which is a harder version of the same discipline.

Next step

Send us the unit size and the office area, separately.