What a clinic fit-out costs, and what DHA asks for.


Medical fit-out in Dubai is quoted at anywhere from AED 600 to AED 1,200 a square foot, which is no help to anyone. This page gives you the approval sequence, our itemised rate card, and a four-room GP clinic priced line by line.

5approval gates, in sequence
13scopes at one government hospital
AED 152–161per sq ft, worked example
2026rates on this page
The honest answer

Why per square foot fails harder for clinics.

Published medical fit-out rates in Dubai sit between AED 600 and AED 1,200 per square foot, and small-clinic totals are quoted from AED 300,000 to AED 1.5 million. A fourfold spread is not a price, it is an admission. The real driver is the share of the floor plate that is clinical, because clinical rooms carry costs that reception and waiting simply do not.

What actually moves the number
  • Pressure regime — neutral consultation rooms are cheap; positive-pressure procedure rooms and negative-pressure isolation and soiled utility are not
  • Sealed flooring — heat-welded homogeneous vinyl, coved and capped, over a tested substrate
  • Sterilisation — a CSSD needs three physically separated zones and a one-way dirty-to-clean route, not floor markings
  • Medical gas — oxygen, vacuum and medical air pipework, pressure-tested, under NFPA-99
  • Radiation shielding — lead-lined partitions for dental and imaging, approved by FANR before installation
  • Clinical handwash basins — one per consultation and treatment room, elbow or sensor operated
What the published ranges hide
  • Whether the unit is a bare shell, a previous clinic, or an office being converted
  • Whether the slab has ever been moisture-tested — the usual cause of a failed clinical floor
  • Existing air-conditioning capacity against the pressure regime the layout needs
  • Whether the fire strategy still works once the floor is subdivided into small rooms
  • Three authority submissions, and a fourth if there is radiation equipment
  • Equipment, furniture and IT, which are often quoted inside a fit-out figure and should not be
Approvals

Five gates, and the order is not negotiable.

The sequence below is where clinic programmes are won or lost. Each gate depends on the one before it, so a drawing error at stage two is discovered at stage five. Confirm the current requirements with DHA and your authority at the start — they move, and we re-check them at every survey rather than working from a saved checklist.

StageWhoWhat it needsTypical duration
1. Building NOCLandlord or owners' associationWritten no-objection to the works, before any authority submissionDays to 2 weeks
2. DHA inactive facility licenceDubai Health Authority, via the Sheryan portalLayout drawings showing reception, waiting, consultation, treatment, sterilisation and clinical waste zonesFrom about a week
3. Fit-out permitDubai Municipality — or the free zone authority in DHCC and similarArchitectural and MEP drawings, licensed contractor10–30 working days
4. Civil Defence approvalDubai Civil DefenceFire detection, suppression, compartmentation and escape drawings — approved before construction starts2–4 weeks
5. DHA pre-licensing inspectionDubai Health AuthorityBuilt facility verified against approved drawings; inactive licence becomes activeAfter practical completion

Imaging, dental X-ray and any radiation source adds a Federal Authority for Nuclear Regulation route that must be cleared before the equipment is installed, not after. DEWA applications run alongside where the supply or metering changes.

Our rate card

The numbers other guides do not publish.

These are our 2026 starting rates, the same ones we quote from. They assume a sound shell, normal access and daytime working. Build your own estimate, then let us survey and fix the price in writing.

ElementUnitFrom
Medical-grade sheet vinyl — heat-welded, 100 mm covedper sq mAED 165
Substrate grinding, levelling and moisture testper sq mAED 40
Anti-slip treatment, wet areas and washroomsper sq mAED 45
Epoxy and PU resin floorsper sq mAED 90
Floor and wall tiling, supply and fixper sq mAED 95
Gypsum partitionsper sq mAED 110
Gypsum false ceilingper sq mAED 85
Moisture-resistant tile ceilingper sq mAED 75
Glazed and frameless partitionsper sq mAED 480
Washable epoxy or PU wall coatingper sq mAED 14
Joinery — reception, nurse station, clean utilityper linear metreAED 1,900
Doors and ironmongery, supplied and hungper leafAED 1,450
Fan coil or split air-conditioning, installedper unitAED 2,400
Ductwork, grilles and pressure balancingper zoneAED 4,500
Distribution board and final circuitsper boardAED 3,500
Lighting and emergency lighting, testedper pointAED 85
Data cabling and nurse-call containmentper pointAED 250
Plumbing, clinical basins and sanitarywareper fixtureAED 450
Fire hose reel and detection interfaceper pointAED 2,800
Signage and wayfindingper signAED 350
Measured survey and clinical space planper unit or floorAED 1,500
3D visualisationper viewAED 1,200
Authority submittals and NOCsper submissionAED 2,500
Strip-out and make-goodper sq mAED 45
Demolition and removalper sq mAED 55
Post-construction cleanper sq mAED 12
As-built drawings and O&M handover fileper projectAED 2,000

All figures exclude VAT and are starting rates for 2026. Medical gas pipework, lead-lined radiation shielding, laminar-flow theatre ventilation, CSSD equipment and clinical furniture are quoted on drawings and are not per-square-metre items.

Worked example

A 150 sq m GP clinic, priced line by line.

Roughly 1,615 square feet. Reception and waiting, four consultation rooms, one minor-procedure room, nurse station and clean utility, soiled utility, clinical waste store and two WCs including one accessible. A previous tenancy stripped back, mid-range specification, daytime working.

LineQuantityRateAmount
Measured survey and space plan1AED 1,500AED 1,500
Authority submittals — DHA Sheryan, DM, Civil Defence3AED 2,500AED 7,500
3D visualisation for the licence submission2 viewsAED 1,200AED 2,400
Strip-out and make-good150 sq mAED 45AED 6,750
Gypsum partitions190 sq mAED 110AED 20,900
Glazed reception and waiting screen12 sq mAED 480AED 5,760
Moisture-resistant false ceiling150 sq mAED 85AED 12,750
Doors and ironmongery, 1,000 mm clear leaves11 leavesAED 1,450AED 15,950
Substrate grinding, levelling and moisture test150 sq mAED 40AED 6,000
Medical-grade sheet vinyl, heat-welded, 100 mm coved150 sq mAED 165AED 24,750
Washable epoxy or PU wall coating420 sq mAED 14AED 5,880
Tiling to WCs and soiled utility38 sq mAED 95AED 3,610
Joinery — reception desk, nurse station, clean utility18 lin mAED 1,900AED 34,200
Air-conditioning — fan coil units5 unitsAED 2,400AED 12,000
Ductwork, grilles and pressure balancing3 zonesAED 4,500AED 13,500
Distribution board and final circuits1 boardAED 3,500AED 3,500
Lighting and emergency lighting, tested72 pointsAED 85AED 6,120
Data cabling and nurse-call containment16 pointsAED 250AED 4,000
Plumbing — clinical handwash basins, WCs, utility sinks14 fixturesAED 450AED 6,300
Fire hose reel and detection interface2 pointsAED 2,800AED 5,600
Signage and wayfinding14 signsAED 350AED 4,900
Post-construction clean150 sq mAED 12AED 1,800
As-built drawings and O&M handover file1AED 2,000AED 2,000
Indicative total, excluding medical gas, shielding and equipmentAED 207,670

That is the measured work only — AED 129 per square foot of elemental cost. It is not the price of the job, and we would rather show you the step than hide it. The reconciliation below takes it to a turnkey figure.

From measured work to a real priceAmountPer sq ft
Elemental sum — the table aboveAED 207,670AED 129
Preliminaries, site establishment, hoarding and dust containment, supervision, insurances, contractor’s overhead and profit — 18% to 25% on a clinic this sizeAED 37,330 to AED 52,330AED 23 to AED 32
Turnkey building works, fixed in writingAED 245,000 to AED 260,000AED 152 to AED 161
Medical gas, radiation shielding, CSSD, clinical furniture, IT and equipmentQuoted on drawings—
A premium medical centre — imaging suite, day-surgery theatre, high-end finishesTwo to three times the aboveOn survey

This is why the published AED 600 to AED 1,200 per square foot figures are not comparable with ours. Those are whole-project numbers — design fees, medical gas, imaging, shielding, sterilisation plant, furniture, IT and equipment, sometimes the licence consultancy too. Strip a clinic back to what a fit-out contractor actually builds and the number is a fraction of it. Ask any contractor quoting you a per-square-foot rate which of those lines is inside it; the answer tells you more than the rate does. The example above is a base-specification GP clinic. Specification alone moves a fit-out rate by a factor of two to three — our office fit-out cost page sets out the same ladder for commercial space.

Design standards

What the clinical rules mean once you have to build them.

Clinical design standards read as a list of dimensions. On site they are a set of cost consequences, and most of them land on the mechanical package rather than the finishes. The figures below are the targets we design and price to; the governing document for your facility is whatever DHA issues for your licence category, and we confirm it before drawing.

SpaceNet area we plan toSupply / exhaust air changesPressure
GP consultation room12–14 sq m6 / 6Neutral
Minor procedure or treatment room14–16 sq m12–15 / 12Positive
Dental operatory10–12 sq mPer equipment and shielding designNeutral
Vaccination roomAbout 12 sq m6 / 6Neutral
Nurse station and clean utility8–10 sq m6–8 / 6Positive
Soiled utility6–8 sq m10–12 / 12, direct exhaustNegative
Isolation examination roomPer layout12 / 12Negative
Clinical waste store4–6 sq mDirect exhaustNegative

Pressure cascades are the reason a clinic needs zoned ductwork and balancing rather than a few split units. Three balanced zones, as in the worked example above, is the practical minimum for a clinic with a procedure room and a soiled utility.

Dimensions that drive the layout
  • Patient corridors at 1,500 mm clear — which sets how much of the floor plate is circulation rather than lettable clinical space
  • 1,000 mm clear door leaves to treatment rooms, 900 mm elsewhere, lever handles, thresholds under 10 mm
  • Step-free route from street or parking to reception
  • One accessible WC per floor, 1,500 mm turning circle, grab rails
  • Procedure-room ceilings commonly at 2.7 m or above, which can conflict with an existing office ceiling void
Finishes that are specification, not preference
  • Homogeneous sheet vinyl, heat-welded seams, 100 mm coved skirting with a capping strip
  • Walls in washable epoxy or PU coating — plasterboard with emulsion is not a clinical finish
  • Moisture-resistant, cleanable ceiling tiles; sealed in positive-pressure rooms
  • One clinical handwash basin per consultation and treatment room, elbow or sensor operated, with integral backsplash and no overflow
  • Sterilisation laid out as three physically separate zones on a one-way dirty-to-clean route
Why us

We build inside hospitals that never close.

Most Dubai fit-out contractors can build a clinic. Rather fewer have worked inside an operational one, and that is where clinic projects actually go wrong — in a medical centre with other tenants, in a hospital wing, in a practice that cannot stop seeing patients.

What we can evidence
  • Thirteen separate scopes awarded at Sheikh Khalifa General Hospital, Umm Al Quwain, across five trades
  • Two completed phases of clinical vinyl worth AED 400K+, with a further AED 500K+ package in delivery
  • Works executed in occupied clinical areas under ICRA and PCRA infection-control protocols
  • Hoarding, dust screening and negative-pressure containment set up before an area is opened
  • Roughly half of delivered value executed in premises that stayed open throughout
  • Registered or approved vendor to federal ministries, government hospitals and a government free zone
How that changes your programme
  • Zone-by-zone handback, so clinical rooms return to use as each zone completes
  • Method statements and risk assessments that a hospital estates team has already accepted
  • Flooring, MEP and finishing self-delivered by our own crews — one accountable party, not four
  • Documentation pack issued per zone at handback, not assembled at the end
  • Substrate moisture testing before any clinical floor is laid, every time
  • A fixed price in writing before mobilisation

We are a young company and we do not pretend otherwise — established January 2025, Dubai DET trade licence 1461423. What we have is a narrow, evidenced specialism in building inside live healthcare facilities, and the repeat awards to show it held up.

Programme

What three to four months actually looks like.

StageTypical durationRuns in parallel with
Measured survey and clinical space plan1 weekLicence category and standards check
Building NOC and DHA inactive licence submission2–4 weeksMunicipality drawing preparation
Municipality fit-out permit10–30 working daysCivil Defence fire drawings, long-lead joinery
Civil Defence approval2–4 weeksMaterial procurement, vinyl and ceiling order
Strip-out and make-good3–5 daysDelivery scheduling
First fix — partitions, MEP containment, ductwork1–2 weeksJoinery manufacture off site
Ceilings, second fix MEP, substrate preparation1–2 weeksMoisture testing
Clinical flooring, welding and coving1 weekJoinery installation
Wall coatings, sanitaryware, signage1 weekAir balancing
Testing, commissioning and Civil Defence inspection1 weekSnagging
DHA pre-licensing inspection and handover1–2 weeksAs-built and O&M file

Build is four to eight weeks of that. Everything else is approvals, which is why we submit in parallel with pricing rather than after award.

Hospital and clinical vinyl flooring

Heat-welded vinyl — how a sealed floor is built

Office fit-out cost in Dubai

Shop and retail fit-out cost

Interior and commercial fit-out

MEP and technical services

Questions

Common questions.

How much does a clinic fit-out cost in Dubai?

Published figures for medical fit-out in Dubai run from roughly AED 600 to AED 1,200 per square foot, and small-clinic totals are quoted anywhere between AED 300,000 and AED 1.5 million. Both ranges are too wide to plan against, because a clinic is not priced by area — it is priced by how much of it is clinical. Our worked example below prices a 150 square metre, four-room GP clinic line by line: AED 207,670 of measured building work, or about AED 152 to AED 161 per square foot turnkey once preliminaries, supervision and contractor’s overhead are added. Medical gas, radiation shielding, sterilisation equipment and clinical furniture sit on top of that — and they are the reason published figures reach AED 600 and beyond. Those are project costs, not building costs. A dental or day-surgery unit of the same size costs substantially more than a GP clinic, and the reason is services, not finishes.

What DHA approvals does a clinic fit-out need?

Five gates, in sequence. A building NOC from the landlord or owners' association; the DHA inactive facility licence applied for through the Sheryan portal, with layout drawings showing reception, waiting, consultation, treatment, sterilisation and clinical waste zones; a Dubai Municipality fit-out permit on architectural and MEP drawings; Dubai Civil Defence approval of the fire and life-safety drawings before construction legally starts; and after the build, the DHA pre-licensing inspection that converts the inactive licence to active. A free zone such as Dubai Healthcare City substitutes its own authority for the municipality stage. Requirements change — we confirm the current set against DHA and the relevant authority at survey rather than working from a checklist.

Which comes first, the licence or the fit-out?

The drawings. This is where most first-time clinic owners lose a month. The DHA inactive licence is applied for on layout drawings, and in practice it needs to be in hand before the municipality permit progresses — so the design has to be right for the clinical standards before anyone prices a partition. Build first and you risk reconfiguring rooms that fail inspection. We produce the measured survey and space plan against the clinical standards, then submit, then build.

Can you fit out a clinic in a building that is still operating?

That is the specific thing we do. Roughly half of what we have delivered has been executed in premises that stayed open, including occupied government hospital wards under ICRA and PCRA infection-control protocols — hoarding, dust screening, negative-pressure zones set up before an area is opened, and clinical space handed back zone by zone. Sheikh Khalifa General Hospital has awarded us thirteen separate scopes across five trades on that basis.

Why does clinical flooring cost more than commercial flooring?

Because it is a sealed system, not a floor covering. Homogeneous sheet vinyl is laid over a ground, levelled and moisture-tested substrate, every seam is heat-welded, and the sheet is coved 100 mm up the wall with a capping strip so there is no open junction anywhere in the room. That is what makes it cleanable to clinical standards, and it is why the rate is AED 165 per square metre rather than AED 95. Skipping the moisture test is the single most common cause of a clinical floor failing within two years.

How long does a clinic fit-out take?

Build is four to eight weeks for a straightforward GP or dental unit. Approvals are the variable and usually the longer half: municipality review runs 10 to 30 working days, Civil Defence and the DHA inspection sit either side of construction, and anything with imaging, an operating theatre or radiation equipment adds a FANR route of its own. Budget three to four months end to end for a first licence, and expect the drawings, not the builders, to set the date.

Do you handle the authority submissions?

Yes — survey, space plan, the submission drawings and the submittals themselves, priced at AED 2,500 per submission in the rate card below. We run them in parallel with pricing rather than after award, which is normally where two to three weeks are recovered.

Next step

Send us the floor plan and we will price it properly.

Floor area, licence category and whether it is a shell, a previous clinic or an office conversion. We survey against the clinical standards, price from the rates on this page, and fix the figure in writing before anything starts.