What a hospitality fit-out actually costs.
An 1,800 square foot restaurant, priced line by line from our own rate card — plus the approvals that set the programme and the reason the kitchen costs three times what the dining room does.
One unit, two completely different rooms.
A restaurant is not a shop with a cooker in it. The front of house prices like retail — finishes, joinery, lighting. The kitchen prices like a light industrial installation with a regulator attached. Averaging them into one rate per square foot produces a number that is wrong for both.
- Joinery density — bar, counters, banquettes, pass, host station
- Ceiling and lighting design, which is most of what a guest notices
- Floor finish — polished concrete, tile, timber or LVT
- Air-conditioning comfort and air distribution at seated height
- Acoustics, which are usually an afterthought and then a complaint
- Shopfront or frontage, where there is one
- Extract canopy, make-up air and fire suppression — the single largest line, and specialist
- Grease trap and drainage falls — AED 6,500 before the drainage runs
- Full-height washable wall finishes and a sealed floor with falls
- Dense power, gas and water services to equipment positions
- A layout that satisfies food-safety flow before it satisfies the chef
- Hand-wash positions, storage separation and waste routes, all inspected
The numbers other guides do not publish.
2026 starting rates, excluding VAT, assuming a sound shell, normal access and daytime working. Build your own estimate, then let us survey and fix the price in writing.
| Element | Unit | From |
|---|---|---|
| Turnkey fit-out, complete package | per sq ft | AED 250 |
| Strip-out and make-good | per sq m | AED 45 |
| Demolition and removal | per sq m | AED 55 |
| Gypsum partitions | per sq m | AED 110 |
| Gypsum false ceiling | per sq m | AED 85 |
| Washable tile ceiling | per sq m | AED 75 |
| Glazed and frameless partitions | per sq m | AED 480 |
| Floor and wall tiling, supply and fix | per sq m | AED 95 |
| Polished concrete | per sq m | AED 85 |
| Epoxy and PU resin floors — kitchens, wet areas | per sq m | AED 90 |
| LVT and vinyl plank | per sq m | AED 95 |
| Anti-slip treatment | per sq m | AED 45 |
| Painting | per sq m | AED 14 |
| Joinery — bar, counters, banquettes, pass | per linear metre | AED 1,900 |
| Doors and ironmongery, supplied and hung | per leaf | AED 1,450 |
| Fan coil or split air-conditioning, installed | per unit | AED 2,400 |
| Ductwork, grilles and air balancing | per zone | AED 4,500 |
| Distribution board and final circuits | per board | AED 3,500 |
| Lighting and emergency lighting, tested | per point | AED 85 |
| Data cabling and POS containment | per point | AED 250 |
| Plumbing and sanitaryware | per fixture | AED 450 |
| Grease trap and drainage | per installation | AED 6,500 |
| Fire hose reel and interface works | per point | AED 2,800 |
| Signage and wayfinding | per sign | AED 350 |
| Measured survey and space plan | per unit | AED 1,500 |
| 3D visualisation | per view | AED 1,200 |
| Authority submittals and NOCs | per submission | AED 2,500 |
| Post-construction clean | per sq m | AED 12 |
| As-built drawings and O&M handover file | per project | AED 2,000 |
Kitchen equipment, extract canopies and their fire suppression, cold rooms, bar cooling, shopfront glazing and specialist lighting are quoted on drawings. They are not per-square-metre items and anyone pricing them that way is guessing.
An 1,800 sq ft restaurant, priced line by line.
Roughly 167 square metres — 110 front of house, 57 kitchen and back of house. A stripped-out previous tenancy, mid-range specification, daytime working.
| Line | Quantity | Rate | Amount |
|---|---|---|---|
| Measured survey and space plan | 1 | AED 1,500 | AED 1,500 |
| Authority submittals — municipality food safety, Civil Defence, landlord | 3 | AED 2,500 | AED 7,500 |
| 3D visualisation | 2 views | AED 1,200 | AED 2,400 |
| Strip-out and make-good | 167 sq m | AED 45 | AED 7,515 |
| Gypsum partitions | 95 sq m | AED 110 | AED 10,450 |
| Gypsum false ceiling — front of house | 110 sq m | AED 85 | AED 9,350 |
| Washable tile ceiling — kitchen and back of house | 57 sq m | AED 75 | AED 4,275 |
| Doors and ironmongery | 7 leaves | AED 1,450 | AED 10,150 |
| Floor tiling — kitchen, stores, WCs | 70 sq m | AED 95 | AED 6,650 |
| Polished concrete — front of house | 110 sq m | AED 85 | AED 9,350 |
| Wall tiling — kitchen, to full height | 60 sq m | AED 95 | AED 5,700 |
| Painting | 320 sq m | AED 14 | AED 4,480 |
| Joinery — bar, counter, banquette bases, pass | 26 lin m | AED 1,900 | AED 49,400 |
| Air-conditioning — fan coil units | 6 units | AED 2,400 | AED 14,400 |
| Ductwork, grilles and air balancing | 3 zones | AED 4,500 | AED 13,500 |
| Distribution boards and final circuits | 2 boards | AED 3,500 | AED 7,000 |
| Lighting and emergency lighting, tested | 85 points | AED 85 | AED 7,225 |
| Data cabling and POS containment | 10 points | AED 250 | AED 2,500 |
| Plumbing — kitchen, bar, WCs | 22 fixtures | AED 450 | AED 9,900 |
| Grease trap and associated drainage | 1 | AED 6,500 | AED 6,500 |
| Fire hose reel and detection interface | 3 points | AED 2,800 | AED 8,400 |
| Signage and wayfinding | 5 signs | AED 350 | AED 1,750 |
| Post-construction clean | 167 sq m | AED 12 | AED 2,004 |
| As-built drawings and O&M handover file | 1 | AED 2,000 | AED 2,000 |
| Elemental sum, excluding kitchen equipment and extract canopy | AED 203,899 |
About AED 113 per square foot of measured work.
| From measured work to a real price | Amount | Per sq ft |
|---|---|---|
| Elemental sum — the table above | AED 203,899 | AED 113 |
| Preliminaries, site establishment, supervision, insurances, contractor’s overhead and profit — 18% to 25% | AED 37,101 to AED 51,101 | AED 21 to AED 28 |
| Turnkey building works, fixed in writing | AED 241,000 to AED 255,000 | AED 134 to AED 142 |
| Kitchen equipment, extract canopy and suppression, cold room, bar cooling | Quoted on drawings | — |
| Night and weekend working, where the unit stays trading | Priced as a visible line | — |
On a fitted-out restaurant, kitchen equipment and the extract package frequently come to as much again as the building works. That is why a single “restaurant fit-out per square foot” figure is close to meaningless unless whoever quotes it tells you which side of that line they are on. Ask.
The permission chain is longer than for any other fit-out.
F&B carries a food-safety regime on top of the normal building approvals, and the kitchen layout has to clear it before anything is built. Confirm the current requirements with your authority — they change, and they vary by emirate and by landlord.
| Approval | Who | What it governs |
|---|---|---|
| Landlord or mall NOC and fit-out permit | Building owner, mall management | Design submission, contractor registration, deposits, working hours |
| Building and fit-out permit | Municipality, or the free zone authority | Architectural and MEP drawings, licensed contractor |
| Food safety approval | Municipality food control | Kitchen layout and flow, finishes, hand-wash positions, storage separation, waste route |
| Civil Defence approval | Civil Defence | Detection, suppression, escape routes, and the kitchen hood suppression system |
| DEWA application | DEWA | Where the electrical load or metering changes — kitchens almost always change it |
| Trade licence covering the activity | Licensing authority | Must be in place before you can trade |
| Hotel classification, where applicable | Tourism authority | Standards for rooms and public areas |
The kitchen layout is the gate. Design it to the food-safety requirements first and the rest of the chain follows; design it to the chef’s preference first and you will redraw it.
Working around service, not instead of it.
Most hospitality work we are asked to price is in a unit that is either still trading or trading next door. Roughly half of everything we have delivered has been executed in premises that stayed open — including occupied government hospital departments under infection-control protocols, which is a harder version of the same discipline.
- Night shifts after last service, with the space returned clean before opening
- Hoarding and dust containment to the landlord’s standard
- Gas, extract and water isolations agreed with the operator in advance
- Deliveries through the service route, in booked slots
- Phased so the kitchen is never out of action longer than agreed
- A named person on site accountable for the morning handback
- Restaurants, cafés and quick-service — front of house and kitchen
- Hotel rooms, corridors and public areas, floor by floor
- Gyms and fitness — floor loading, impact flooring, high fresh-air rates
- Salons and spas — plumbing density, wet areas, ventilation
- Bars and lounges — joinery, acoustics, bar cooling interfaces
- Staff accommodation and back-of-house areas
Shop, retail and showroom fit-out cost
Clinic and medical centre fit-out cost
Epoxy and resin floors for kitchens and wet areas
Common questions.
How much does a restaurant fit-out cost in Dubai?
Our worked example below prices an 1,800 square foot restaurant line by line: AED 203,899 of measured building work, or about AED 241000 to AED 255000 turnkey once preliminaries, night working and contractor’s overhead are added. That excludes the two biggest variables in any F&B job — the kitchen equipment and the extract canopy — which are specified by your kitchen consultant and quoted on drawings. A café with a reduced kitchen comes in well below it; a hotel restaurant with a show kitchen comes in well above.
Can you work while we stay open?
Yes, and in hospitality that is usually the whole brief. Night shifts after last service, hoarding and dust containment, extract and gas isolations agreed with the operator, and the space cleaned and returned every morning before opening. Night and weekend working carries a labour premium — we show it as its own line rather than hiding it in the rate, because it is a decision you should get to make.
What approvals does an F&B fit-out need?
More than any other commercial fit-out. A landlord or mall NOC and fit-out permit; a municipality building and fit-out permit; food safety approval of the kitchen layout, which governs flow, finishes, hand-wash positions and storage; Civil Defence approval of fire detection, suppression and the kitchen hood system; a DEWA application where the load changes; and a trade licence covering the activity before you can open. Requirements change and vary by emirate and by landlord — we confirm the current set at survey rather than working from a saved checklist.
Why is the kitchen so much more expensive per square metre than the dining room?
Because it is a wet, hot, heavily serviced room with a regulator looking at it. Full-height wall tiling, a washable sealed floor with falls to drainage, a grease trap, an extract canopy with fire suppression, make-up air, dense power and plumbing, and a layout that has to satisfy a food-safety inspector before it satisfies a chef. A dining room is finishes and lighting. A kitchen is services with finishes attached.
Do you do hotel rooms and public areas?
Yes, and the same discipline applies as in a hospital: a floor at a time, guests and staff separated from the works, noise windows agreed, and each room or zone handed back complete rather than left part-finished. Roughly half of everything we have delivered has been executed in premises that stayed open, including occupied government hospital departments under infection-control protocols. A hotel corridor is a gentler version of the same problem.
What about gyms, salons and spas?
Common and straightforward, with three things that catch people out: floor loading and impact absorption where free weights are involved, ventilation and fresh-air rates that are higher than a normal commercial space, and plumbing density in wet areas — showers, wash stations, steam rooms — which drives both cost and programme. We have delivered and currently quote work in this category.
How long does a hospitality fit-out take?
Six to ten weeks on site for a restaurant or café of this size once approvals are in hand, with the kitchen as the critical path. Approvals typically add four to eight weeks and run in parallel. The long-lead items that actually set the date are the extract canopy, bespoke joinery and anything imported — we identify those at survey, not at order.
Can you maintain it after opening?
Yes, and in F&B you want that agreed before you open rather than after the first breakdown. Commercial AMC starts at AED 7,500 a year for a unit of this size, covering air-conditioning, plumbing, electrical and building items, with a four-hour emergency response written into the contract. Grease trap servicing and extract cleaning are scoped separately because their frequency is set by use, not by the calendar.
Send us the unit size and the kitchen layout.
The kitchen decides the programme and most of the cost, so that is where we start. We survey, price from the rates on this page, and fix the figure in writing before anything begins.